​Update renovation works 15 October

Posted on 0 October, 2018

The new Starter cabin is rain and weatherproof.
Except for the roof, which needs some further finishing touches, the outside look of the cabin is finished.

The works inside are on schedule, the new insulated walls, preliminary electricity and heating related work is finished. Next week they will pour the concrete for the floor.